IASSC Black Belt Control Phase Practice Questions: 7 Worked Questions with Explanations

Control carries 22% of the Black Belt exam under the official syllabus: Lean controls, the full statistical process control family (including Xbar-S, CuSum and EWMA charts and rare-event charts), and Six Sigma control plans. Our bank holds 330 Control questions; these seven worked questions are drawn from that bank — including a p-chart limits item with the full computation shown — with the correct answer and a full explanation for each.

Worked questions

1. A bottling team asks why their CuSum caught a filler drift three shifts before the X-bar chart showed anything. Which explanation is accurate?

A. The X-bar chart was defective, because any shift a CuSum can detect must also breach three-sigma limits in the same subgroup where the filler drift first appeared.

B. The CuSum limits were narrower because they had been computed from a smaller sample than the X-bar chart limits

C. The drift added a modest surplus to the cumulative sum every subgroup, while each individual subgroup mean still sat comfortably inside the wide Shewhart limits

D. Filler drift changes the process range first, and CuSum charts are actually range charts that respond to spread changes

Correct: C. Shewhart limits judge each subgroup in isolation against roughly three-sigma bounds; a small steady bias stays inside them while the CuSum total keeps growing.

2. A stable process suddenly shows a point at 4.2 sigma on an individuals chart, with the next points back near centre. Which chart family member most likely produced the fastest signal for this event?

A. The EWMA with lambda 0.1 signals fastest, because its tight steady-state limits turn a diluted movement into an immediate signal for that 4.2 sigma spike.

B. The CuSum, because a single large deviation instantly fills the decision interval regardless of the allowance

C. None of them, because a point that recovers on its own is defined as common-cause and charts must not signal it

D. The individuals chart itself, because a lone extreme point breaches Shewhart limits at once while smoothed statistics only move partway toward it

Correct: D. Isolated spikes are Shewhart territory: memory charts discount a single point by design, trading spike speed for drift sensitivity.

3. Escape cost for a solder defect is estimated at 120 dollars per escaped unit in warranty handling. A proposed in-process test costs 2 dollars per unit on 1,000 units monthly and would cut escapes from 30 to 5 units monthly. Is it justified?

A. No: a per-unit test costing two dollars cannot be justified while escapes affect fewer than five percent of the thousand units shipped each month

B. Yes, but only because any test that reduces escapes at all must be adopted regardless of its cost

C. Yes: escapes avoided save 25 times 120, which is 3,000 dollars, against 2,000 dollars of test cost, leaving about 1,000 dollars monthly net benefit

D. No: the saving is 25 times 2 dollars, which is 50 dollars, far below the test's monthly expense

Correct: C. Avoided escapes: (30 – 5) x 120 = 3,000. Test cost: 2 x 1,000 = 2,000. Net is about 1,000 dollars monthly in the test's favour.

4. Two connectors in a harness look alike but carry different circuits, and cross-connection causes rework. What device selection shows sound judgment?

A. Slow the line's cycle time so operators have more seconds to distinguish the connectors by inspection

B. Color-code the connectors and train operators to check colors, accepting occasional swaps as inevitable

C. Key the connectors with incompatible shapes so each plug physically fits only its correct socket

D. Add a warning label to the harness drawing, which is the least costly response and sufficient for look-alike parts

Correct: C. When parts invite mix-ups, shape-based prevention (a contact method) beats vigilance-based warnings that rely on attention.

5. An andon system logs pulls reliably, but the same station stops for the same fault every day and nothing changes. Which system element is missing?

A. A louder signal, because repeated faults persist only when the alert is not noticeable enough for support staff working elsewhere in the facility

B. A rule limiting each station to two pulls per week, forcing operators to solve recurring faults themselves without involving support functions repeatedly

C. A second andon board in the manager's office, since visibility to senior leadership alone is sufficient to eliminate recurring stop causes

D. An escalation and problem-solving loop that converts repeated signals into assigned countermeasures with deadlines reviewed at the daily tier meeting

Correct: D. Andon without a response system is just noise recording. Repeated signals must escalate into owned, dated countermeasures, or the same fault returns daily forever.

6. A p chart has center line 0.05. For a subgroup of 100 the limits are computed, then a subgroup of 400 arrives. How do the limits for the larger subgroup compare?

A. They are narrower: the standard error halves when sample size quadruples, so the upper limit falls from about 0.1154 to about 0.0827 here

B. They are wider, because larger subgroups accumulate more defectives and therefore require more generous boundaries to avoid false alarms daily

C. They are identical, because p chart limits are drawn once from the center line and never adjusted for differing subgroup sizes in practice

D. They cannot be computed for mixed sizes, so the 400-unit subgroup must be discarded or split into four artificial subgroups of one hundred

Correct: A. SE for n=100 = sqrt(0.05 x 0.95/100) = 0.0218, UCL = 0.1154. For n=400, SE = 0.0109, UCL = 0.0827. Larger samples estimate the proportion more precisely, tightening limits.

7. A g chart for surgical site infections shows a point at zero opportunities between two infections occurring on consecutive cases. How should this extreme point be handled?

A. Treat it as the chart's strongest worsening signal: back-to-back events are exactly the clustering the g chart exists to expose

B. Delete it as an outlier, because zero gaps distort the chart and two infections in a row are too demoralizing to display to the clinical team

C. Average it with the previous gap before plotting, since single points on rare-event charts are never interpreted without smoothing beforehand

D. Convert the chart to a p chart for the month, because a zero gap proves the event rate is no longer rare enough for g chart methodology

Correct: A. On opportunities-between charts, the smallest values carry the alarm: consecutive events mean the protective system failed twice running. Suppressing the point would hide the clearest signal available.

A note on format. The real IASSC exam mixes multiple-choice with true/false questions, while PassProfessor’s bank trains you with four-option multiple-choice questions throughout — the same knowledge, in a format that forces you to discriminate between close alternatives. No worked set on this page reproduces the real exam’s item-type mix.

These questions are drawn from the same bank as the full program. Start with the 20 free sample questions (also presented readably on the free sample questions page), read the IASSC Black Belt exam guide, then see the full IASSC Lean Six Sigma Black Belt Exam Prep program — 1,500 original questions built at the official syllabus weights (Define 13% · Measure 21% · Analyze 27% · Improve 17% · Control 22%), with an explanation for every answer, for $59 with 6 months of access.

Disclaimer

PassProfessor is an independent exam-preparation provider. This program is exam preparation only: it is not the real exam, it provides no education credit, and completing it does not by itself qualify you for any license or certification. The real exam is run by its own exam body — you register for it, pay its fees, and sit it through that body, not through PassProfessor. All practice questions in this program are original; they are not actual exam questions.